Project Update (PDF)

Project Update

Front Door

Plans for the Church of the Nazarene’s new Global Ministry Center were unveiled during the 84th annual session of the General Board on February 24, 2007 in Kansas City. A multimedia report from 360 Architecture staff, legal representation from Lathrop & Gage L.C., financial officers representing Bank of America, and members of the Walton Construction Company L.L.C., provided overviews, pertaining to their respective areas, of the project.

At approximately 109,000 square feet, the two-story Global Ministry Center located on 38 acres at 17001 Prairie Star Parkway in Lenexa, Kansas, will function as the administrative hub in supporting personnel, churches, missions, and ministries around the world. To be completed in fall 2008 in conjunction with the denomination’s Centennial, the center is being created for long-term and flexible use.

According to General Secretary Jack Stone, helpful direction on this project is coming from Zimmer Real Estate Services. The company provided guidance in the process of securing 360 Architecture and Walton Construction, premier architectural and construction companies in the Kansas City area. Additionally, the Zimmer group has partnered with the church to market the 6401 The Paseo property in Kansas City.

General Treasurer Marilyn J. McCool reported that Bank of America, with whom the General Board has a long history, was chosen as the financial partner. Bank of America offered a tax-exempt bond financing, issued through the city of Lenexa, with the bank purchasing the bonds. Along with these transactions, the church was able receive an attractive financial package with significant savings to the church over the life of the loan.

Marvin Manlove, principal of 360 Architecture, addressed three key areas affecting the firm’s approach to this project:

  1. Using efficient and effective solutions supporting best business practices
  2. Recognizing the center needs to serve the church for many years—built to last and to allow flexibility in support of ongoing ministry needs in a changing world
  3. Creating a collaborative environment allowing staff and visitors means of communicating around issues important to the church’s ministries and administrative needs

    John Gaar, building designer, noted that as the center is constructed, care is being taken to protect the natural surroundings. He stated, “We want to be good stewards not just to the church, but also to the earth and community.”

    Nazarene Theological Seminary (NTS) and Nazarene Publishing House (NPH) have chosen to remain at their current locations in Kansas City. The Global Ministry Center acreage does provide for future development for NTS and NPH should those entities choose to relocate there in the future.

    In 2006, the denomination’s General Board took action gifting the Commons, King Conference Center, and two adjacent houses to NTS for the purpose of extending their campus. Other Headquarters-owned homes across the street from the campus have been made available to NTS for less than 50 percent of market value.

    The current Headquarters property is a multi-acre complex with three aging office buildings, the first of which was built in the 1950s. After considerable research, prayer, and professional guidance, the General Board voted in 2005 for the relocation. The decision was made under the direction of the Board of General Superintendents and General Board Executive Committee.

    Friends and constituents of the Church of the Nazarene are providing financial gifts and pledges, representing a worldwide effort in support of the denomination’s administrative center. In 2006, Japanese and South Korean Nazarenes provided the impetus for additional financial support as they led the way in key donations. World Mission regions led off with a $1 million commitment. General Board members, Headquarters employees, individuals, churches, districts, and Nazarene institutions have added to the gifts.

    According to General Secretary Jack Stone, helpful direction on this project is coming from Zimmer Real Estate Services. The company provided guidance in the process of securing 360 Architecture and Walton Construction, premier architectural and construction companies in the Kansas City area. Additionally, the Zimmer group has partnered with the church to market the 6401 The Paseo property in Kansas City.

    General Treasurer Marilyn J. McCool reported that Bank of America, with whom the General Board has a long history, was chosen as the financial partner. Bank of America offered a tax-exempt bond financing, issued through the city of Lenexa, with the bank purchasing the bonds. Along with these transactions, the church was able receive an attractive financial package with significant savings to the church over the life of the loan.

    Marvin Manlove, principal of 360 Architecture, addressed three key areas affecting the firm’s approach to this project:

    1. Using efficient and effective solutions supporting best business practices
    2. Recognizing the center needs to serve the church for many years—built to last and to allow flexibility in support of ongoing ministry needs in a changing world
    3. Creating a collaborative environment allowing staff and visitors means of communicating around issues important to the church’s ministries and administrative needs

    John Gaar, building designer, noted that as the center is constructed, care is being taken to protect the natural surroundings. He stated, “We want to be good stewards not just to the church, but also to the earth and community.”

    Nazarene Theological Seminary (NTS) and Nazarene Publishing House (NPH) have chosen to remain at their current locations in Kansas City. The Global Ministry Center acreage does provide for future development for NTS and NPH should those entities choose to relocate there in the future.

    In 2006, the denomination’s General Board took action gifting the Commons, King Conference Center, and two adjacent houses to NTS for the purpose of extending their campus. Other Headquarters-owned homes across the street from the campus have been made available to NTS for less than 50 percent of market value.

    The current Headquarters property is a multi-acre complex with three aging office buildings, the first of which was built in the 1950s. After considerable research, prayer, and professional guidance, the General Board voted in 2005 for the relocation. The decision was made under the direction of the Board of General Superintendents and General Board Executive Committee.

    Friends and constituents of the Church of the Nazarene are providing financial gifts and pledges, representing a worldwide effort in support of the denomination’s administrative center. In 2006, Japanese and South Korean Nazarenes provided the impetus for additional financial support as they led the way in key donations. World Mission regions led off with a $1 million commitment. General Board members, Headquarters employees, individuals, churches, districts, and Nazarene institutions have added to the gifts.

    Groundbreaking(PDF)

    Groundbreaking

    February 2006 Board of General Superintendents break ground on the GMC

    Several hundred Nazarenes representing all world regions gathered on Sunday, February 26, for a commemorative groundbreaking ceremony at the site of the future Global Ministry for the Church of the Nazarene. Members and guests of the denomination’s General Board met under a tent raised at and in Kansas, for this event. The groundbreaking launches a historic step for the denomination and sets in motion a process that will lead to the eventual construction of the new facility.

    In his opening remarks, General Superintendent Jerry D. Porter stated,

    "Today, we gather from around the world to visually and symbolically launch this historic endeavor for our denominational family. As we approach our centennial in 2008, we are mindful of that great cloud of witnesses who have gone before us to share the Good News of Jesus Christ with people everywhere. In fact, we are here because someone cared and introduced us to Jesus. That mission compels us—it is not primarily about a physical building, but rather, a Global Ministry that will foster productive global disciple-making endeavors."
    Four leadership groups raised their shovels and turned the soil at the site: The Board of General Superintendents, the Executive Committee of the General Board, the Global Mission Team, and the World Mission Regional Directors. Additionally, General Superintendents Emeriti W. Talmadge Johnson and Donald D. Owens participated in the ceremony. Reflecting on the event, General Secretary shared, “Breaking ground for a new Global Ministry reflects the beginning of new opportunities for resourcing the Church of the Nazarene around the world. We praise God for His leadership to this moment and trust His continued guidance as we focus on fulfilling the Great Commission.” Fundraising for the Global Ministry has already begun. According to General Treasurer Marilyn J. McCool, “Pledges from the six world regions have been received, with the Church of the Nazarene in East Asia leading the way with pledges from and Japan. We are now presented with a once-in-a-lifetime opportunity to participate in the creation of the new Global Ministry through our gifts.” Responding to this vision, during their Sunday evening meeting on February 26, General Board members and guests pledged nearly $200,000 ) (U.S.) for the Global Ministry Center.

    During their 2005 session, General Board members voted to relocate the Church of the Nazarene’s Headquarters. The action came about after three years of study and a recommendation from consultants that the church Headquarters remain in the area.

    Nazarene Headquarters has been located at 6401 The Paseo, Missouri, for over half a century. The denomination remains committed to discovering community-benefiting uses for the present property in Missouri. In their recent meetings, the Executive Committee of the General Board voted to work in concert with the Kansas City Economic Development Office in this endeavor.

    A Vision Beyond Their Horizons PDF ICON SMALL

    A Vision Beyond Their Horizons

    Rev. & Mrs. Higuchi with violin

    On March 11, 2007, the Church of the Nazarene in Japan celebrated 100 years of ministry in a magnificent display of appreciation for its heritage, and with great expectation for the future. During the past century, Japan has undergone drastic economic and social changes that have been accompanied by changes in religion. The nation experienced three wars. Yet, in the midst of intense suffering, the Church of the Nazarene in Japan never lost its identity as a major force in the Wesleyan-Holiness movement and its spiritual life. The Church of the Nazarene in Japan has been led by devoted ministers and lay leaders who distinguished themselves by their courage and commitment. Among them were such leaders as pastors Nobumi Isayama and Hiroshi Kitagawa.

    More than symbolic of this commitment to the mission and message of the church were the recent responses of two devoted Japanese Nazarenes—an ordained minister, and a dedicated layperson, whose Nazarene roots are deeply embedded in the history of the church in that land. Motoko Araki, born in 1923, is the daughter of Nobumi Isayama, who was a leading figure in the beginning of the Church of the Nazarene in Japan. Motoko was baptized by her father in 1941. Following graduation from Arwin College, she began a teaching career. By 1956 she was teacher and principal of the Oyamadai Nazarene Kindergarten, a school from which 5,000 students have graduated. Upon learning that funds were needed to build the denomination’s Global Ministry Center (GMC) in Lenexa, Kansas, she gave $10,000* toward the project. She likes the idea of calling the new administrative and ministries campus a “Global Ministry Center.” As a life-long member of the Church of the Nazarene, and in memory of her father, she wants to be a part of this vision.

    Shigeru Higuchi, a distinguished pastor and church leader, was born in 1924 in Hikone City of the Shiga Prefecture. He was converted and baptized in 1945 and shortly afterward completed theological studies in Chiba. After pioneering churches in the Chiba Prefecture, over a 10-year span he developed the work of the church. During those years, he organized the Naha church and four others. In 1959, he was ordained by General Superintendent Hugh C. Benner. In l991 Shigeru was elected district superintendent of the Japan District, a role in which he served for four years. Following this assignment he became director of the district office in Tokyo, where he still serves. An accomplished violinist, Shigeru owned a certified antique violin manufactured in Cremona, Italy, by Kaathaina Abbuhl, a world-renowned violin maker. When Shigeru learned of the GMC, he was moved by the Holy Spirit—and as he said, “the Nazarene spirit”—to sell his precious violin and contribute $10,000 toward the creation of the center. These two gifts from Japanese Nazarenes, and $10,000 from the Anjung Church of the Nazarene in South Korea, are some of the earliest cash gifts for the project. Such sacrificial and heart-felt gifts are representative of the unity found in the international church and are providing inspiration for the global denomination.



    By Donald D. Owens, General Superintendent Emeritus of the Church of the Nazarene.

    Used with permission, Holiness Today.

    *All amounts expressed in U.S. dollars.

    Church of the Nazarene Markets Headquarters Property

    Church of the Nazarene Markets Headquarters Property

    October 2006

    The Church of the Nazarene has listed its International Headquarters campus in Kansas City on the market for sale. Zimmer Real Estate Services, L.C. is serving as the exclusive listing agent for the property. Currently, approximately 265 employees operate out of three office buildings.

    According to Jack Stone, general secretary for the Church of the Nazarene, "Teamwork in the mission of the Church of the Nazarene can be greatly improved through a new building that will bring the entire staff under one roof."

    In April, Zimmer was selected to provide development management services to the Church of the Nazarene during the development and construction of the new Global Ministry Center near 95th Street and Renner Boulevard in Lenexa, Kansas. This site is approximately 14 miles west of the current location. Construction is expected to be complete in 2008. The transition from an International Headquarters to the new Global Ministry Center will allow the Church of the Nazarene to best resource the ministries in over 150 world areas from this administrative facility.

    Nazarene Theological Seminary and Nazarene Publishing House will remain at their current locations in Kansas City.

    In 2006, the denomination's General Board took action gifting the Commons, King Conference Center, and two adjacent houses to Nazarene Theological Seminary for the purpose of extending their campus.

    The General Board voted in 2005 to relocate Headquarters to the Lenexa site under the direction of the Board of General Superintendents and General Board Executive Committee.


    --Global Ministry Center Communications

    Construction Phase Update

    Global Ministry Center
    Construction Phase Update

    GMC - 4th Illustrater Door Right 45

    The Church of the Nazarene is working in partnership with Walton Construction, 360 Architects, and Zimmer Real Estate Services for the construction of the Global Ministry Center. The following are highlights of the new building’s progress now under development in Lenexa, Kansas.

    • Final building design has been approved by the owner (Church of the Nazarene).
    • Construction and contract documents were bid by Walton, the church’s construction manager, and construction costs (bids) are within the budget.
    • All site development, sewer and building permits have been secured from the City of Lenexa, State of Kansas, and utilities.
    • Site grading is nearing completion.
    • Footings and foundations for the building are in process.
    • The start of the structural steel installation is scheduled for fall 2007.
    • The building remains on schedule for completion and occupancy in conjunction with the Church of the Nazarene’s Centennial in the fall of 2008.
    Acts in AfricaPDF ICON SMALL

    Acts in Africa

    by Ted R. Lee
    Africa Tree


    It had been a long flight from Indianapolis to my destination in the Horn of Africa where I had been invited to be a part of a District Superintendents’ and Pastors’ Conference. I did not know what to expect when I arrived in this area known for the mighty movement of God despite resistance to the gospel. Granted, stories abounded about the amazing things God was doing there. But I had no idea that I was about to witness a scene from the Book of Acts lived out in the 21st century.

    After I arrived, I met World Mission Director Louie E. Bustle and General Superintendent Jesse C. Middendorf and together, we were driven to the Nazarene mission station. According to the general superintendent, a district assembly the day before had concluded with over 12,300 new members received by profession of faith and an increase of about 33,000 in attendance. The district superintendent reported that they had planted nearly 600 churches and indicated a goal to plant 1,000 more churches in the next assembly year. This church multiplication was on my mind as we threaded our way through the sprawling city and finally arrived at the mission station, which had been built by Work and Witness teams. We were briefed on our assignments and on what we could expect during the conference. Although I was prepared academically, I was not prepared emotionally for what I was about to experience.

    Two hundred and twenty-four pastors attended the conference. Evening services were open to anyone who wanted to attend. For many of the pastors, transportation involved walking for nearly two weeks to be a part of this event. One pastor walked for 13 days in order to be a part of the event, but arrived several days late. He apologized to his district superintendent then quickly explained the reason for his late arrival. En route to the conference, he had planted five churches and would appoint a leader in each of the churches on his way home.

    I have never witnessed such joy, singing, praising, and praying in all of my life as I rejoiced with my brothers and sisters in Christ there in the Horn of Africa. When I learned of the hardships and the persecution that many of them experience, it was not easy for me to speak on my assigned subjects of education, humility, and servanthood.

    During the final service, a national missionary presented the message from Acts 2 concerning the coming of the Holy Spirit to fill and empower the lives of the believers. The power of those words from the day of Pentecost to the present examples, was deeply moving. What an incredible worship time it was. As the service came to what I expected to be the close, the missionary said there was one final item needing attention. Speaking in regard to the International Church of the Nazarene, he shared how we were all family and needed each other. He reminded his listeners how blessed they were in receiving help for many years from the denominational leaders who sent missionaries to share the love of Jesus Christ. The speaker informed them that the denomination’s General Board had voted to build a much-needed Global Ministry Center, which would be of great benefit in helping to spread this message of salvation.

    Then, the missionary challenged audience members to empty their pockets so they could be active participants in this important project. Those of us who were guests had no idea that this offering was going to be taken. When the gifts were counted, they had $181 (U.S.) and one wristwatch. I wept.

    The next day, I left as a changed person. I’ll never be the same, for I saw the Book of Acts lived out before me. My Christian family had been extended by meeting and worshipping with my brothers and sisters in the Horn of Africa. Their faith in giving to something they saw as bigger than themselves is unforgettable.



    Ted R. Lee is superintendent of the Indianapolis District.
    Used with permission, Holiness Today.
    Editor’s Note: Construction of the Global Ministry Center is in progress. Once completed, the Church of the Nazarene International Headquarters will relocate to that site.

    January 2008 Status Summary
    The following update on the Global Ministry Center in Lenexa, Kansas, provides a project update as of January 2008.
    Overall Project Status Summary
    • The project remains on schedule to open in the fall of 2008.
    • The general building design is complete (core, shell, and interiors).
    • As previously reported, the Church of the Nazarene commissioned Scott Rice Office Works to provide space planning design that addresses systems furniture layouts, demountable partition locations, and adjacencies. That work is progressing well and is nearing completion.
    • The chapel has been designed as a one-story structure within the main atrium and will be a focal point as people enter the atrium.
    • A visitor center is also being designed within the GMC’s atrium space. This is intended, in part, to convey messages about the history and ongoing mission of the Church of the Nazarene.
    Construction Progress
    Permits
    • All critical construction permits have been secured by Walton Construction.
    Site Work
    • Walton Construction started the site work on April 30, 2007. This is about 95 percent complete and remains on schedule
    • Rough and mass grading are substantially complete.
    • Concrete curbs and gutters, and asphalt paving are approximately 90 percent complete.
    • Walton Construction has scheduled the installation of landscape material such as trees, shrubs, plant materials, and turf for the spring and summer of 2008. This will provide a somewhat “established” landscape when the building is occupied and operational later this year
    Utilities
    • This includes storm and sanitary sewers, electric power distribution, and the water main extension.
    Building
    • All footings and foundations are substantially complete.
    • All three major structural steel sections of the building are nearing completion. Steel installation should be completed within a month.
    • The majority of the concrete slabs on grade are complete with the exception of the atrium area. Some of the elevated structural concrete slabs have been installed for the second floor level.
    • Walton has started installation of perimeter metal stud wall framing along with the installation of the exterior wall sheathing.
    • Site lighting is basically complete.
    • Windows are scheduled for installation in April 2008.
    • Walton expects the building to be fully enclosed and “weather tight,” with the exception of the stone veneer, during April 2008.
    • An exterior wall mockup has been completed. Exterior limestone samples have been approved.
    • Exterior stone wall installation of native Kansas limestone should start within the next few weeks.
    March 2008 Status Summary

    GET TO KNOW STEVE JULO

    Picture of Julo Meet Steve Julo, the senior project manager with Walton Construction for the Global Ministry Center (GMC). Recently, GMC Communications interviewed Steve as a means of introducing him to employees at Nazarene Headquarters. In addition, he provides insights into the project.

    Q. Explain your role with the GMC.
    A. Project oversight. Utilizing my experience and knowledge to assist the project team in avoiding potentially costly mistakes, I work to ensure that the budget and schedule goals are met. Also, I act as an extra set of ears in listening to the many challenges that a project such as this faces, and then offer feedback. It is also my responsibility, at the appropriate time, to apply pressure as necessary to push everyone into making timely decisions that are in the best interest of the project overall.
    Q. What makes this project unique?
    A. The needs of the client. Everyone on the team is excited to be constructing a project for a client whose primary focus for the building is that it has a 50-year-plus life cycle. This project allows everyone to utilize their expertise to construct a building that will be standing long after most of us have retired from the industry.
    Q. Define “50-year” building.
    A. It is important for the design team and contractor to have an understanding the client needs for the building. By defining the GMC building as a 50-year building, we inform the design team and contractor that the materials and method of construction utilized need to be of the highest quality and built to last. Many buildings constructed today are not intended to last 50 years and are instead built with the understanding that in 1020 years, major renovation and/or a complete rebuild will be necessary. Materials for this project were selected based on life cycle costs more than the initial “front end” costs.
    Q. Where you raised?
    A. I was born in Kansas City, Missouri, but I spent the majority of my youth in Grandview, Missouri.
    Q. Did you play with Legos as a child?
    A. I don’t recall playing with Legos. I enjoyed being outside and spent most of my time playing sports, mostly baseball. I built tree houses in my backyard, none of which had a 50-year life cycle. By the time I got done with one project, I was ready to tear it down and start the next one, so I was more of a short-term developer.
    Q. Tell us about your background in the business.
    A. As a young teen, I started working with my father who was in the residential remodeling business. After high school, I went to Central Missouri State University (CMSU) where I earned a B.S. in construction management. Prior to graduation, I was offered an opportunity stay at CMSU to instruct four courses and assist in another as a graduate assistant. I took advantage of the opportunity afforded me and earned an M.S. in industrial technology. While attending CMSU, I worked as an intern for the Department of Defense at Whiteman Air Force Base where I was employed by the federal government and represented its interest in several construction projects on the base. After earning my graduate degree, I interviewed with companies in the Kansas City area until I found the right fit for me. I have been at Walton for over seven years and have worked on a wide array of projects (office, retail, governmental, hospitality, and so on) in that time.
    Q. What prompted your interest in the construction industry?
    A. I have always been a very mechanical person and enjoyed putting things together and taking things apart. Also, I need a challenge or I become bored very quickly. The construction industry is never boring. My position also allows me to spend a good deal of time with another of my passions, teaching. I enjoy the opportunity to help train and educate the people who work with me, or in some cases, clients who do not construct buildings for a living.
    Q. Are will still on track for an October opening?
    A. Yes.
    Q. What is significant about the Church of the Nazarene connecting with Walton?
    A. Walton is one of the 50 largest (revenue) general builders in the U.S. We are large enough to tackle any project, but we pride ourselves in making each of our clients feel that they have 100 percent of our attention. Based out of Kansas City, we have five other offices and have work over a good portion of the U.S.
    Q. On a daily average, how many workers are on the GMC site?
    A. Walton has one project manager, one project engineer, one project superintendent, one carpenter foreman, one administrative assistant (who splits her time between three projects), and one project accountant (who splits her time as well) on site full time. The number of other workers will vary from day to day depending on the stage of construction. Field workers vary in number from 20100 depending on what activities are occurring on a particular day.
    Q. How are we creating a building that is affordable, attractive, durable, and employeeand guest-friendly?
    A. The approach that was taken from the beginning of the project is allowing the building to be constructed in the most economical manner while also ensuring that the owner (Church of the Nazarene) is making the best long-term decisions. Walton became a member of the project team at about the same time as 360 Architects so we were able to provide a cost to every decision, helping the owner to make informed decisions every step of the way. In addition to the initial construction costs, Walton worked with the design team to look at life cycle costs of various materials and equipment. This allowed the owner to get most building out of their budget both now and in the future.
    Q. Is it true that this is the best project you have now?
    A. When it is said and done, this will probably be the best project of which I have ever been a part. The project itself is unique. We are being allowed to construct a building using a combination of the latest technology with high quality materials that have been used for centuries. The construction team on this project makes my job easy. Also, we have an excellent relationship with the owner.
    Q. Where do things stand with the construction progress?
    A. Work on the primary building structure is 95 percent or more complete with minimal roof decking and miscellaneous steel detailing work yet to be completed. The exterior “skin” of the building (metal stud framing and sheathing) is approximately 50 percent complete. Work on the metal roofing and stone façade started in February. Installation of the membrane roofing and window systems began in early March.

    At the first floor interior of the building, a substantial amount of wall framing has been completed. Rough-in work on that floor is well underway for the fire sprinkler and electrical systems. The parking lots and roadways have been completed with the exception of the front circle drive, which will be completed soon. Roughly, the overall site work is around 85 percent complete. Landscaping and irrigation work will also begin this spring.

    Q. Review unique elements about the construction materials:
    A. There are many unique materials and/or construction methods in use on this project:

    1. The storm water drainage system design incorporates two bio-retention basins that act as filters by keeping pollutants from traveling downstream into the water table. Also, there are two dry-detention basins in use that are built with amended soils to again filter storm water before it leaves the site and travels into the local water supply.
    2. The building façade is framed at a 5 percent slope for aesthetic reasons, which is fairly unique, and is clad with native Kansas stone in a random ashler pattern.
    3. Two large skylights and clerestory windows allow natural light to flow into the building core. The glass is energy efficient to block harmful UV infiltration.
    4. The majority of the building is on an access floor system that will allow great flexibility with in-floor modular power/data and ventilation. The HVAC system is primarily an underfloor air system, which is more user-friendly and efficient than a typical overhead ducted system.
    5. A large number of the interior walls are a demountable or moveable wall system that in theory are more flexible than hard walls as they can be relocated when and if necessary.
    Q. Are you a member of related professional groups?
    A. Yes the American Society of Healthcare Engineers, Design Build Institute of America, and American Society of Military Engineers
    Q. What’s your dream or ideal building project?
    A. If I were writing the script of the ideal construction project for me I would want: 1) a qualified and cooperative project team, 2) a unique project something that I would be proud to show my family and friends, 3) a safe project 100 percent of everyone that worked on the project goes home each night to their families in the same shape they were in when they came to work. The GMC project has several attributes of my dream project.
    Q. Share about your immediate family.
    A. My wife, Rachel, and I have been married for over six years. We have a three-year-old daughter, Isabel, and a one-year-old son, Landon.
    Q. What’s on your iPod?
    A. I am a rock and roll guy, mostly. With over 10,000 songs on my iPod, my tastes are a little eclectic (Frank Sinatra, Jimi Hendrix, and George Strait are all there), but when I am by myself, I enjoy listening to Led Zeppelin or some new band that will probably never have an album on the Billboard charts.
    Q. Favorite TV shows?
    A. When I watch TV, it is generally related to sports. I probably watched more than 90 Kansas City Royals games last year.
    Q. Favorite pro and college sports teams?
    A. Missouri Tigers football and basketball, and the Kansas City Royals and Chiefs.
    Headquarters Transition Update

    HEADQUARTERS TRANSITION UPDATE

    In their 2006 meeting, the General Board approved the recommendation of the Executive Committee to gift the Church of the Nazarene Headquarters-owned Nazarene Commons, King Conference Center, and two residences on the west side of Woodland Avenue to Nazarene Theological Seminary (NTS), to accommodate their campus continuity. Both entities are located on adjoining campuses in Kansas City, Missouri.

    Additionally, the General Board has owned most of the houses on the east side of Woodland (between Meyer and 63rd Street), and NTS was given opportunity to purchase those properties at a reasonable cost.

    In order to accommodate the changes anticipated for these properties by NTS in time for the beginning of the fall semester, the King Conference Center and Nazarene Commons will be transferred to NTS as of June 1.

    The Nazarene Commons will no longer provide food service as of June 1. NTS will begin to redesign this building this summer and once the remodeling is finished, the building will re-open in August as a coffee shop and student center.

    NTS plans to continue operating the King Conference Center as it is currently used.

    The property transfer is due to Headquarters relocating to the Global Ministry Center (GMC), which is under construction in Lenexa, Kansas. At approximately 109,000 square feet, the two-story GMC will function as the administrative hub in supporting personnel, churches, missions, and ministries around the world. To be completed in fall 2008 in conjunction with the denomination's Centennial, this center is being created for long-term, flexible use.

    --GMC Communications

    Project Update

    Project Status May 2008

    Following is a comprehensive project update on the Global Ministry Center (GMC) in Lenexa, Kansas, as of May 2008. The details here provide a glimpse into the myriad of details and scope of such a project.


    E-Mail: globalministrycenter@nazarene.org


    Section I Overall Project Status Summary
    • The project remains on schedule to open in the fall of 2008.
    • The guaranteed maximum price (GMP) for construction remains under the construction budget.
    • General building design (core, shell, and interiors) is complete.
    • Scott Rice Office Works has finalized finishing touches on the "space planning" designs that address systems furniture layouts, demountable partition locations, and adjacencies. Product orders for furnishings are being processed.
    • Terracon Consulting has provided testing of the concrete's strength and also special inspections for the quality of the structural steel installations. Terracon's responsibility was to verify that the strength of the concrete in the GMC and all structural steel connections are in compliance with those specified by the structural engineer of record.
    • The Church of the Nazarene has retained Display Studios to design the "Visitor Center" located within the GMC's atrium. The purpose of the GMC visitor center is: To share the Church of the Nazarene story and mission with guests and employees in a way that will engage and encourage the viewers, motivating them to make Christlike disciples in the nations. It is the intent that this purpose will be reached through interactive displays, photographs, artifacts, video, audio, and will include an international connection. This feature within the atrium space will be a centerpiece of the new GMC.
    • LocationLink has been retained as a consultant to the Church of the Nazarene to manage the actual move and relocation process from Headquarters to the GMC. LocationLink successfully managed the move of all personnel into the new H&R Block corporate office building in downtown Kansas City.
    Section II Construction Progress

    Permits

    All critical construction permits have been secured by Walton Construction.

    Site Work

    As previously reported, Walton started the site work about a year ago on April 30, 2007. The site work is approximately 95 percent complete, has progressed as expected, and remains on schedule.

    • Rough grading/mass grading is 100 percent complete.
    • Installation of landscape materials has begun.
    • URS Corporation has provided geotechnical services and soil testing for the church on the site. The majority of the URS test results meet or exceed specified requirements.
    • Installation of concrete curbs and gutters, and asphalt paving is approximately 95 percent complete.
    Utilities

    All site utilities are substantially complete.

    Building
    • All footings and foundations are complete including the chapel foundations in the atrium.
    • Structural steel framing is 95 percent complete.
    • The majority of the perimeter steel stud and exterior wall sheathing is substantially complete.
    • The native limestone exterior walls continue to be installed on schedule. This adds an attractive indigenous, durable exterior wall to the GMC.
    • Concrete floor slab installations are substantially complete.
    • Exterior window framing and glazing (glass) is nearing completion.
    • All flat roofing installations are substantially complete.
    • The installation of the sloped standing seam metal roofing around the perimeter of the building has started.
    • The aluminum framing for the clearstory windows around the top of the atrium ceiling has started.
    • All interior "rough-in" installations such as metal stud walls, mechanical, plumbing, and electrical are well underway.
    • The building will be "in the dry" within the next two weeks, which means that the building is then essentially weather tight.
    • Installation of the raised access floor will start within the next month.
    • Walton Construction remains on schedule for completion of the building in the fall of 2008.
    Parking Lot

    Over 350 parking spaces are available in the two adjoining GMC parking lots.

    Looking to the next 30 days:
    • The GMC will be enclosed and weather tight. The significance of this milestone is that it will allow Walton Construction to start many other interior installations that could not be started otherwise.
    • Interior mechanical, plumbing, and electrical rough-in will continue.
    • Chapel construction will continue.
    • Installation will occur in the following areas—
      • Raised access floors
      • Landscape
      • Network cabling
      • Interior steel stairs
      • Interior steel guardrails (around the perimeter of the level two floors adjacent to the atrium)
    —GMC Communications
    Peruvians Give Over $11,000 for GMC

    Peruvian Nazarenes Give Over $11,000 to Global Ministry Center

    Recently, $11,000 (USD) was raised by the Church of the Nazarene in Peru for the denomination's new Global Ministry Center (GMC). According to Christian Sarmiento, South America regional director, and Segundo Rimarachin, field strategy coordinator for Peru, the Peruvian church held a special offering for the GMC in connection with the Nazarene Centennial celebration.

    The Church of the Nazarene in Peru has a strong history and tradition. In 1914, pioneer missionary Roger Winans and his wife, Mary, went to Peru. Today, the country has a Peruvian leader serving as field strategy coordinator and a full membership of 53,503.

    Marilyn J. McCool, general treasurer for the Church of the Nazarene said of the offering, "We are grateful for the generosity reflected in this gift from Peruvian Nazarenes. This wonderful offering will blessed by God for use in the Global Ministry Center, which will resource Nazarene ministries around the world."

    The GMC, located in Lenexa, Kansas, will serve as the administrative hub for the Church of the Nazarene, supporting the denomination's faith initiatives.

    --NCN SAM and GMC Communications
    Eastern Michigan Pledges $100,000.00 to GMC

    Eastern Michigan Pledges $100,000 to Global Ministry Center

    Stephen T. Anthony, superintendent of the Eastern Michigan District presented General Superintendent Nina G. Gunter with a check for US$57,000.00 on April 26 to assist in developing the denomination's new Global Ministry Center (GMC).

    The funds, representing $1,000 for each year of the district's existence, were presented during Eastern Michigan's 57th annual assembly. Anthony challenged the district to pledge US$100,000.00 to the new GMC to be paid by the Church of the Nazarene's centennial event in 2008. Each of the 75 churches on the district participated in the pledge efforts.

    In his annual report, Anthony challenged, "I am proposing that 100 percent of our churches of Eastern Michigan either build into their budgets or receive offerings in support of our new Global Ministry Center. I believe that Eastern Michigan Nazarenes will give generously and the total should equal or exceed $100,000.00. In honor of our 57th anniversary, I have proposed to the District Advisory Board, and they have unanimously supported, taking money earned from our Nazarene Foundation to get us more than halfway to our goal."

    Anthony reminded the assembly members and guests that they were a part of the international Church of the Nazarene and had this opportunity to share the message of holiness around the world through their participation in the GMC.

    The new GMC will be located in Lenexa, Kansas. A groundbreaking ceremony was held in February. Additional information about the GMC is available via E-mail at .

    Move Update

    From Headquarters to
    Global Ministry Center

    The employees and functions of Nazarene Headquarters (Kansas City, Missouri) will be moving to the new Global Ministry Center (GMC) of the Church of the Nazarene in Lenexa, Kansas, during September 11-13. In order to prepare for packing and transition, some Headquarters functions will begin to be unavailable in advance of those dates.

    For example, the collections in the Nazarene Archives are being moved by the end of August to the new storage facility near the GMC. Therefore, the Archives staff is unable to respond to research requests until the transition to and settling in at the GMC is complete (probably around September 30).

    Visitor tours of Nazarene Headquarters have been suspended due to the current status of the buildings as moving preparations escalate. Tours of the GMC will begin to be available around mid-October.

    During the move weekend in September, staff will not be working from Headquarters or the GMC. If an emergency need arises during these dates, please leave a voice mail message at the following number: 816-333-7000, extension 2517. Messages will be checked several times each day. The appropriate department’s representative will be advised accordingly.

    The Church of the Nazarene is committed to having minimal interruption of service to constituents. However, some responses may be delayed as records are retrieved and equipment connection is restored.

    Church of the Nazarene
    Global Ministry Center
    17001 Prairie Star Parkway
    Lenexa, KS 66220

    913-577-0500
    Specific prayer is requested during the transition:
    • For the safety of those involved
    • For the staff as they make adjustments inherent in such a move
    • For the continued blessing on the work of the worldwide Church of the Nazarene

    The Global Ministry Center exists because of God's blessings, and in order to support the efforts to make Christlike disciples in all the nations.


    David Wilson
    General Secretary
    Church of the Nazarene

    Moving in

    Completing the Task

    Headquarters to Global Ministry Center

    As of September 15, the Church of the Nazarene is operating its administrative offices for worldwide ministries from the Global Ministry Center (GMC) in Lenexa, Kansas. On the opening day employees were welcomed by the Board of General Superintendents. Members of that Board led the group in a time of worship, giving thanks for God's blessing on the work and vision that led to the creation and occupancy of the GMC.

    General Superintendent Jesse C. Middendorf, Board chair with jurisdiction over the GMC, stated, "What a thrill it is to experience the reality of moving from Headquarters to Global Ministry Center. This is a new day for the Church of the Nazarene. How fitting that we are now operating from the GMC as we celebrate our Centennial and begin writing the history of our second century from such a beautiful and functional facility. General Treasurer Marilyn McCool has done an exceptional job with the task of project leader and as a denomination we are indebted to her and to everyone involved in this challenging task."

    In addition to the GMC employee group, all regional directors were on site for the opening event. Representing the six World Mission regions were Gustavo Crocker (Eurasia), Eugenio Duarte (Africa), Carlos Saenz (Mexico and Central America), Christian Sarmiento (South America), John Smee (Caribbean), and Verne Ward III (Asia-Pacific). The presence of this group helped connect, in spirit, the entire Nazarene family.

    At approximately 109,000 square feet, the two-story GMC is located on 38 acres and functions as an administrative hub in supporting Nazarene personnel, churches, missions, and ministries around the world.

    The concept was to have the facility completed this fall in conjunction with the denomination's Centennial, which is being celebrated around the world on Sunday, October 5.

    A key purpose of the GMC is to function as a collaborative and flexible environment allowing staff and visitors various means of communicating around issues important to the church's ministries and administrative needs.

    The property that operated as the Church of the Nazarene International Headquarters previously is a multi-acre complex in Kansas City, Missouri, with three office buildings, the first of which was built in the 1950s. After considerable research, prayer, and professional guidance, the General Board voted in 2005 for the relocation. The decision was made under the direction of the Board of General Superintendents and the General Board Executive Committee.

    Nazarene Theological Seminary (NTS) and Nazarene Publishing House (NPH) have chosen to remain at their current locations in Kansas City. The GMC acreage allows for future development of NTS and NPH should those entities choose to relocate there in the future.

    Friends and constituents of the Church of the Nazarene continue to provide financial gifts and pledges representing a worldwide effort in support of the denomination's administrative center. In 2006, Japanese and South Korean Nazarenes provided the impetus for additional financial support as they led the way in key donations. World Mission regions provided a $1 million (USD) commitment. General Board members, GMC employees, individuals, churches, districts, and Nazarene institutions are adding to the gifts.

    Church of the Nazarene
    Global Ministry Center
    17001 Prairie Star Parkway
    Lenexa, KS 66220

    913-577-0500
    --GMC Communications
    Why a GMC?
    WHAT: At approximately 109,000 square feet, the two-story Global Ministry Center will function as the administrative hub. Its purpose is to support personnel, local churches, missions, and ministries around the world, including schools and education, hospitals and other medical care, training and development programs, and disaster relief efforts. The center is being created for long-term and flexible use.
    WHERE: The Global Ministry Center site near I-435 at 95th and Renner in Lenexa, Kansas, is approximately 14 miles from the current Headquarters location in Kansas City, Missouri.
    (Actual address: 17001 Prairie Star Parkway)
    WHEN: Plans are to have the relocation completed in conjunction with the denomination’s Centennial celebration in October 2008.
    WHY: The current Headquarters property is a multi-acre complex with three aging office buildings, the first of which was built in the 1950s. After considerable research, prayer, and professional guidance, the General Board voted for the relocation in 2005.
    WHO: Although the center will provide a vital working environment for employees, all Nazarenes will be welcome to visit and to share in the purpose and ministry of this administrative hub for the Church of the Nazarene.
    DETAILS: Additional information on the transition, new building, questions, and donation opportunities are available on the web at http://www.nazareneglobalministrycenter.org/.
    Property Sale

    Church of the Nazarene Announces Property Sale
    Ministry Center Paseo

    The Church of the Nazarene is announcing the sale of a parcel of property at 63rd Street and Woodland in Kansas City, Missouri, to Brookside Day and Charter School. This parcel is part of the property at 6401 The Paseo, the former home of the Church of the Nazarene International Headquarters.

    "The Paseo property Ministries Building was sold to the Kansas City Brookside Day and Charter School at fair market value leaving a community legacy of child education. The Paseo campus remains on the market for sale, either in whole or in parcels," said General Treasurer Marilyn J. McCool.

    Brookside Day School was founded in 1956 serving children in preschool, and became a charter school in 2002. The school offered the earliest extended-care programs in Kansas City. Brookside is noted for high quality academic programs in addition to excellent childcare services. The school is dedicated to serving the educational and extended care needs of the children and families of the Greater Kansas City Metropolitan area.

    Brookside, which serves classes from kindergarten through seventh grade, is sponsored by the University of Missouri-Kansas City and is a member of the Basic School Network.

    This sale represents one of the goals in selling The Paseo property, which was to secure a new owner intent on having a vital presence in the community.

    In September 2008, the denomination took occupancy of its newly-constructed Global Ministry Center at 95th Street and Renner Boulevard in Lenexa, Kansas. This site is approximately 14 miles west of the previous location.

    The transition from the Headquarters campus, with three office buildings, to the Global Ministry Center, with the denominational entities in one building, allows the church to better resource ministries in over 151 world areas from this administrative facility. Zimmer Real Estate Services, L.C. is the exclusive listing agent for The Paseo property.

    -Global Ministry Center Communications

    GMC Dedication

    Global Ministry Center Dedication

    Dedication of Global Ministry Center GMC

    The Church of the Nazarene celebrated the Global Ministry Center (GMC) dedication on Sunday, February 22 in Lenexa, Kansas. Planned as a part of the 86th session of the denomination's General Board, the gathering included representatives from around the world who joined in praise and thanksgiving for the completion and purpose of the building.

    John Bowling, president of Olivet Nazarene University and chairperson of the General Board's executive committee, read greetings from Motoko Matsuda, superintendent of the Japan District. Following Bowling's welcome, General Superintendent Nina G. Gunter gave the invocation.

    General Superintendents James H. Diehl and Jerry D. Porter read scriptures in English, Spanish, and Portuguese. These included passages recognizing the praise of the people, God's direction in the Church's foundation, support, light, and purpose for existence: "Therefore go and make disciples of all nations" Matthew 28:19.

    In presenting the dedication address, General Superintendent Paul G. Cunningham reminded attendees of God's faithfulness to the Church when he shared, "When you don't know what to do, you go to God because He always knows what to do."

    Cunningham reflected on Acts chapter 12, which points to Peter's release from prison. The believers could not believe Peter was actually in their midst, although they had been praying for his prison release. "Pray until you hear the knock at the door, then open the door and be obedient," challenged Cunningham.

    The prayer of dedication was offered by General Superintendent Jesse C. Middendorf, who thanked God for His provisions in bringing the Church of the Nazarene to this point with the new administration center, relocation from the former Headquarters property, and for Nazarenes around the world engaged in ongoing ministries.

    Centennial Heritage Awards were given to the Board of General Superintendent emeriti members and surviving spouses of deceased emeriti by General Superintendent J. K. Warrick. Those in attendance included W. Talmadge and Genell Johnson, Donald D. and Adeline Owens, and Madelyn Hurn. Warrick commended the emeriti group stating, "We are carrying out the building of the church from the foundations you helped to set." The award is an original, limited edition lithograph, which was designed specifically for the denomination's Centennial.

    General Treasurer Marilyn J. McCool introduced professional partnerships and representatives from the various groups including Walton Construction, 360 Architecture, Scott Rice Office Works, Zimmer Real Estate Services, and Display Studios. Banking partners were also introduced.

    In addition, McCool recognized employees who served on the building project's GMC Leadership Team. She served as GMC project leader, Larry Morris was the project coordinator. David Wilson, Judy Veigl, and Don Walter also served on the committee. Former General Secretary Jack Stone served until his retirement.

    In addition, McCool acknowledged the GMC employees who served as members of the Internal Planning and Design Committee including the chairperson, Don Walter, Jackie Berdych, Mike Fetting, David Hayse, Rich Houseal, Larry Morris, Carmen Ringhiser, and Judy Veigl.

    Speaking in recognition of GMC donors, McCool stated, "Lead gifts include those from two donors who gave million dollar matching gifts. Other gifts came from the Board of General Superintendents, General Board members, employees, Nazarene Publishing House, Nazarene educational institutions, laity, friends, churches, and districts around the world."

    Bowling welcomed Lenexa Mayor Michael Boehm. The mayor and McCool then unveiled a bronze dedication plaque. Listed on the plaque are names and statements that will assist future visitors and employees in understanding this unique moment in Church of the Nazarene history represented by the dedication, and by the building's completion in the denomination's Centennial year.

    General Secretary David P. Wilson closed the event with remarks fitting the occasion and offered the benediction.

    -GMC Communications

    Zambian Church Raises Funds For GMC

    Zambian Church Raises Funds For GMC

    GMC Zambia Article Photo
    Photo By: Gary Sidle

    Chilenje Nazarene church treasurer Doreen Phiri presents the church's GMC donation to General Superintendent Jerry D. Porter, and his wife Toni."

    Recently, the Zambia District held its ordination service at the Chilenje Church of the Nazarene in Lusaka. At the close of the event, the Chilenje congregation presented a gift to General Superintendent Jerry D. Porter for the denomination's new Global Ministry Center (GMC).

    Presenting the gift was Doreen Phiri, church treasurer, who stated, "We as Chilenje Church of the Nazarene are proud to be associated with the building of the new global center. Through our giving and with great joy, we contribute this amount of 1 million Zambian Kwacha (ZK)" (approximately $190 USD).

    The church simply wanted to do what they could to be a part of the international church and support the new GMC. Pastor Raymond Chirwa explained that the church held special offerings every Sunday in January and February. They then made the presentation to Porter once they had reached the goal of 1 million ZK.

    The Chilenje Church is one of the oldest Nazarene Churches in Zambia and has been a leader for Zambian Nazarenes. Chilenje is also the home the Madalisto Choir that has represented Africa twice at the denomination's general assemblies. This gift is another indication of how the Chilenje Church, along with the broader African church, engages in a missional mindset, supporting the work of the church around the world.

    Missionary Gary Sidle said of the donation, "We give God the glory for the response of His church to making a difference throughout the world for Christ."

    The newly-constructed GMC, located in Lenexa, Kansas, serves as the administrative hub for the international Church of the Nazarene.

    --GMC Communications

    Updates
    Stories of Faith
    Powered